Optimasi Waktu Dan Biaya Dengan Kombinasi Metode Kerja Menggunakan Alat Berat Pada Pekerjaan Timbunan Main Dam Proyek Pembangunan Bendungan Tapin, Kalsel
DOI:
https://doi.org/10.61722/jssr.v1i2.270Keywords:
: Factors, Delays in Project Land Acquisition, TCTO, Tapin Dam Water Structure, South KalimantanAbstract
Delays in completing a construction project often occur. One of the factors that can cause delays in development is that there are problems with land acquisition which cause the implementer/contractor to be unable to start carrying out work. Delays in project completion generally always result in losses, such as increasing costs, hampering operating profits resulting from the project, reducing the possibility of the implementer being able to start a new project, and can have an impact on the image of the implementer. The aim of this research is to speed up the duration of the implementation of the Main Dam Embankment Work for the Tapin Dam Construction Project, South Kalimantan.
The research method used is an analysis of the existing work network and the relationship between time and cost in the process of accelerating work implementation using the time cost trade off method, namely by alternatively changing the combination of heavy equipment methods used using the help of the Microsoft Project program to determine the critical path.
Based on acceleration by adding tools, the most effective is adding tools using ADT, because it produces the fastest completion time with a duration of 360 days but with an additional cost that is greater than the normal cost, namely IDR. 801.952.935. Compared to the normal cost of Rp. 767,651,068,342 and with a normal duration of 1000 days, the result is an additional cost of Rp. 34,301,867,554 with a reduced duration of 620 days.
References
A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) Third. (2004). Project Management Institute.
Atchison, S. (2011). Using Microsoft Project 2010. America : United States of America.
Darmadi, A. (2021). Analisa Percepatan Durasi dengan Metode "Time Cost Trade Off" pada Proyek Peningkatan Jalan Bukit Seribu (Lapen-Rigid) Kota Samarinda. KURVA S: Jurnal Keilmuan dan Aplikasi Teknik Sipil, 11(1), 527-
Dipohusodo, I. (1996). Manajemen Proyek & Konstruksi Jilid 2. Yogyakarta: Kanisius.
DPN APINDO. (2007). Gambaran Umum Produktivitas. Jakarta: Knowledge Sharing Forum.
Eddy, H. (2003). Manajemen Produksi dan Operasi, Edisi Terbaru. Grasindo .
Ervianto, W. I. (2002). Manajemen Proyek Konstruksi. Yogyakarta: Andi.
Ervianto, W. I. (2005). Manajemen Proyek Konstruksi. Yogyakarta: Andi.
Frederika, A. (2010). Analisis Percepatan Pelaksanaan dengan Menambah Jam kerja ptimum pada Proyek Konstruksi. Jurnal Ilmiah Teknik Sipil.
Heizer, J., & Render, B. (2005). Operations Management. Jakarta: Salemba Empat.
Husen, A. (2010). Manajemen Proyek.
Yogyakarta: ANDI.
Husen, A. (2011). Manajemen Proyek : Perencanaan, Penjadwalan, dan. Yogyakarta: ANDI.
Ibrahim, H. B. (2001). Rencana Dan Estimate Real of Cost. Jakarta: Bumi Aksara.
Jeffery L. Whitten, L. D. (2004). Metode Desain & Analisis Sistem. Yogyakarta: Andi.
Keputusan Menteri Tenaga Kerja dan Transmigrasi, R. (n.d.). Nomor Kep.102/Men/VI/2004 tentang Waktu Kerja Lembur dan Upah Kerja Lembur.
Kisworo, R. W. (2016). Analisis Percepatan Proyek Menggunakan Metode Time Cost Trade Off Dengan Penambahan Jam Kerja Lembur Dan Jumlah Alat (Studi Kasus: Proyek Pembangunan Jalan Tol Solo--Semarang, Ruas Bawen--Solo Seksi II.
Kusumanto, I. P. (2016). Perbaikan Metode Kerja Untuk Meningkatkan Produktivitas Kerja Operator Pada Stasiun Pengemasan Di CV. Mie Sohun Ichlas. Jurnal Teknik Industri. Fakultas Sains dan Teknologi. UIN Sultan Syarif Kasim. Riau, 2(2), 175-186.
Laksono, T. D. (2007). Produktivitas Pada Proyek Konstruksi. Teodolita (Media Komunikasi Ilmiah di Bidang Teknik), 8(2).
Luthan, A. L., & Syafriandi. (2006). Aplikasi Microsoft Project untuk Penjadwalan Kerja Proyek Teknik Sipil. Yogyakarta: Andi offset.
Maharani, L., & Fajarwati. (2006). Analisis Optimasi Percepatan Durasi.Mela, A. F., Kustiani, I., & Ma'ruf, A. (2016). Analisis Time Cost Trade Off untuk Mengejar
Keterlambatan Pelaksanaan Proyek di Bandar Lampung. Jurnal Rekayasa, 20(2).
Nurhayati. (2010). Manajemen Proyek Cetakan Pertama. Yogyakarta: Graha Ilmu.
Nurjaman, H. D. (2014). Manajemen Proyek. Indonesia: PUSTAKA SETIA.
Nurjaman, K., & Dimyati, H. (2014). Manajemen Proyek. Bandung: Pustaka Setia.
O’Brien, J. J., & Plotnick, F. L. (2010).
CPM in construction
management. McGraw-Hill Education.
Peraturan Menteri Tenaga Kerja. (1996).
Nomor : PER.05/MEN/1996
Tentang Sistem Manajemen Keselamatan dan Kesehatan Kerja .
Proboyo, B. (1999). Keterlambatan Waktu Pelaksanaan Proyek Klasifikasi dan Peringkat dari Penyebab- penyebabnya. Civil Engineering Dimension, 1(1), 46-58.
Rahayu, F. A. (2020). Percepatan Jadwal Menggunakan Sistem Lembur Dengan Precedence Diagramming Method (Studi Kasus: Proyek Pembangunan Bendungan Pidekso Yang Terletak Di Kabupaten Wonogiri Provinsi Jawa Tengah). Universitas Muhammadiyah Yogyakarta.
Rani, H. A. (2016). Manajemen Proyek Konstruksi. Yogyakarta: CV. Budi Utama.
Rani, I. (2014). Analisis Perbandingan Percepatan Pelaksanaan Pekerjaan Ditinjau Dari Penambahan Tenaga Kerja Dan Penambahan Jam Kerja Pada Proyek PembangunanGedung ITERA Tahap I. Skripsi : Universitas Lampung.
Riduwan. (2002). Skala Pengukuran Variabel-Variabel Penelitian. Bandung: Alfabeta.
Rizky, F. M., Sarya, G., & Beatrix, M. (2019). Analisis Biaya dengan Metode Time Cost Trade Off pada Proyek Konstruksi Supermall Pakuwon Indah Phase 4 Anderson Surabaya.
Rochmanhadi. (1984). Perhitungan Biaya Pelaksanaan Pekerjaan dengan Menggunakan Alat-Alat Berat. Departemen Pekerjaan Umum, Jakarta.
Rochmanhadi, I. (1984). Perhitungan Biaya Pelaksanaan Pekerjaan Dengan Menggunakan Alat-Alat Berat.
Rostiyanti, S. F. (2002). Alat Berat Untuk Proyek Konstruksi. Jakarta: Rineka Cipta.
Sanjaya, H., & Johari, G. J. (2021). Analisis Optimalisasi Perencanaan Kembali Durasi dan Biaya Proyek Menggunakan Metode Pertukaran Waktu dan Biaya. Jurnal Konstruksi, 347- 354.
Santosa, B. (2013). Manajemen Proyek : Konsep & Implementasi. Yogyakarta: Graha Ilmu.
Setyama, D. D. (2020). Analisis Percepatan Durasi Pada Proyek Pembangunan Bendungan Bendo, Ponorogo-Jawa Timur Dengan Menggunakan Metode Time Cost Trade Off. Universitas Gadjah Mada.
Sjafri, M. (2007). Manajemen Mutu SDM.
Jakarta: PT. Ghalia Indonesia.
SNI-DT-91-0010-2007. (2007). Tata Cara
Perhitungan Harga Satuan Pekerjaan Plesteran Untuk Konstruksi Bangunan Gedung dan Perumahan. SIMS, DPU, Jakarta.Soeharto, I. (1995). Manajemen Proyek dari Konseptual Sampai Operasional. Jakarta: Erlangga.
Soekirno, P. (2000). Metode Konstruksi I, Bangunan, Sistem Struktur, Teknologi dan Metode Konstruksi. Diktat Kuliah Magister Teknik Sipil UII, Yogyakarta.
Sugiyono. (2019). Metode Penelitian Kuantitatif, Kualitatif dan R&D. Bandung: Alfabeta.
Sugiyono. (2019). Statistika untuk Penelitian. Bandung: CV. Alfabeta.
Suherman. (2016). Optimasi Waktu dan Biaya Menggunakan Metode Time Cost Trade Off pada Proyek Access Road Construction and Soil Clean Up. Jurnal Teknik Industri: Jurnal Hasil Penelitian dan Karya Ilmiah dalam Bidang Teknik Industri, 2(2), 199-211.
Tjaturono, Nadjadji, A., & Indrasurya, B. (2004). Evaluasi Produktivitas Tenaga Kerja Berdasarkan Delapan Faktor Internal Dibandingkan Dengan Standar BOW 1921 dan SNI 2001 pada Pembangunan Rumah Menengah di Jawa Timur. Jurnal Teknik Sipil Universitas Tarumanagara Jakarta, Maret.
Wale, P. M., Jain, N. D., Godhani, N. R., Beniwal, S. R., & Mir, A. A. (2015). Planning and Scheduling of Project using Microsoft Project:Case Study of a Building in. IOSR Journal of Mechanical and Civil Engineering (IOSR- JMCE), Volume 12(Issue 3 Ver.III), 57-63.
Widyatmoko, Y. (2008). Analisis Percepatan Waktu Menggunakan Metode Crashing pada Kegiatan Pemancangan di Proyek Dermaga 115 Tanjung Priok dengan Aplikasi Program PERTMASTER. Skripsi : Universitas Indonesia.
Wignjosoebroto, S. (1995). Ergonomi, Studi Gerak dan Waktu, Edisi Pertama. Surabaya: PT. Guna Widya.
Wignjosoebroto, S. (2000). Ergonomi, Studi Gerak dan Waktu Teknik Analisis untuk Meningkatkan Produktivitas Kerja. Jakarta: PT. Gunawidya.
Wilopo, D. (2009). Metode Konstruksi dan Alat-alat Berat. Jakarta: Universitas Indonesia.
.
Downloads
Published
Issue
Section
License
Copyright (c) 2023 JOURNAL SAINS STUDENT RESEARCH

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.