Studi Faktor-Faktor Penyebab Keterlambatan Pengadaan Tanah Dan Pengaruhnya Terhadap Waktu Pelaksanaan Proyek Pembangunan Bendungan Bagong Paket 1 Di Kabupaten Trenggalek (MYC)
DOI:
https://doi.org/10.61722/jssr.v1i2.297Keywords:
Delay in Project Land Acquisition, Bagong Dam Package 1, SIDLACOMAbstract
Development problems in Indonesia are divided into two large parts, namely the problem of development objects and the problem of subjects who will carry out development. The problems that originate from the subject of development are procurement. The problem of providing land is very vulnerable in its handling, because it concerns the lives of many people. If we look at the government's need for land for development purposes, it can be understood that the available state land is very limited, therefore the only way that can be taken is by liberate land belonging to the community, whether it has been authorized by rights based on Customary Law or other rights. The method used for data processing in this research is a mixed method (mixed methodology), namely a combination of qualitative and quantitative methods. Quantitative methods were used to describe technical data at the research location. At the stage of explaining land acquisition issues, a qualitative approach was taken because it tends to be very subjective. This research was conducted by applying SIDLACOM.
Based on the research results, in the Bagong dam construction project there were several problems in the land acquisition process, including social problems, technical problems, financial problems and administrative problems. In the Bagong Dam construction project, social problems and administrative problems were the main keys in causing delays in land acquisition, thereby causing delays in the construction project. The solution for handling delays in land acquisition is that first, accurate research needs to be carried out to determine the value of compensation by considering the location of the land, criteria for land and buildings, land use, quality of buildings, and the economic conditions of the affected communities. Second, improve coordination between related parties. Third, carry out appropriate and repeated socialization. And fourth, conduct good negotiations.
References
A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) Third. (2004). Project Management Institute.
Abdurrahman. (1983). Masalah Hak-hak Atas Tanah dan Pembebasan Tanah di Indonesia (Vol. Cet. 2). Bandung: Alumni.
Ade-Surya, T., & Wirabrata, A. (2011). Masalah Kebijakan dalam Pengadaan Tanah untuk Pembangunan Infrastruktur. . Jurnal Ekonomi dan Kebijakan Publik, 729-751.
Ahmed, S., Azhar, S., Kappagntula, P., & Gollapudil, D. (2003). Delays In Construction: a Brief Study of the Florida Construction Industry. Proceedings of the 39th Annual ASCConference, Clemson University (p. 293). Clemson: SC.
Alim, A. (2022, Juli 7). Progres Pembangunan Tiga Dihaji Capai 34 Persen, Ini Kendala yang Dihadapi. Retrieved Juli 16, 2023, from Rmol Sumsel: https://www.rmolsumsel.id/
Badrulzaman, M. D. (1983). KUHPerdata Buku III Hukum Perikatan Dengan Penjelasan. Bandung: Ikatan Alumni.
Dajan, A. (1986). Pengantar Metode Statistik II. Jakarta: LP3ES.
Dipohusodo, I. (1996). Manajemen Proyek & Konstruksi Jilid 2.
Elsam. (2019, Maret 15). Bendungan Pamukkulu: Air Dibendung, Tanah Hilang, HAM Dilanggar. Retrieved Jui 16, 2023, from Elsam : Lembaga Studi & Advokasi Masyarakat: https://elsam.or.id/uncategorized/bendungan-pamukkulu-air-dibendung-tanah-hilang-ham-dilanggar
Ervianto, W. I. (2002). Manajemen Proyek Konstruksi, Edisi Pertama. Yogyakarta: Salemba Empat.
Ervianto, W. I. (2005). Manajemen Proyek Konstruksi. Yogyakarta: Andi.
Harsono. (2007). Hukum Agrarian Indonesia Sejarah Pembentukan Undang-Undang Pokok Agrarian, Isi dan Pelaksanaanya (Vols. Ed. Rev., cet. 11). Jakarta: Djambatan.
Henong, S. B. (2017). Identifikasi Faktor-Faktor Risiko pada Bendungan Raknamo di Kabupaten Kupang. Konferensi Nasional Teknik Sipil dan Infrastukrur. Jurusan Teknik Sipil Universitas Jember.
KabarTimur. (2021, Agustus 18). Bendungan Way Apu Terkendala. Retrieved Juli 16, 2023, from Kabar Timur News: https://www.kabartimurnews.com/2021/08/18/bendungan-way-apu-terkendala/
Kamaruzzaman, F. (2012). Studi Keterlambatan Penyelesaian Proyek Konstruksi. Jurnal Teknik Sipil Untan, 175-190.
Keputusan Menteri Pekerjaan Umum No. 67/KPTS/1998. (1998). Tentang Petunjuk Prektis Pengendalian Pelaksanaan Proyek di Bidang Pekerjaan Umum untuk Para Pimpinan Proyek/Bagian Proyek.
Khofiyah, O. L. (2019). Pengaruh Pembebasan Tanah terhadap Keterlambatan Proyek Pembangunan Jalan Tol Studi Kasus: Jalan Tol Cinere-Jagorawi Seksi II B. Media Komunikasi Teknik Sipil, 191-198.
Kuntari, D. R. (2003). Tesis: Pengaruh Proses Pembebasan Tanah Terhadap Kinerja Proyek Perumahan. Depok: Program Studi Teknik Sipil Kekhususan Manajemen Konstruksi, Program Pasca Sarjana Bidang Ilmu Teknik UI.
Kurniawan, F., Wulandari, D. A., & Ayu, L. A. (2018). Studi Kasus Keterlambatan Proyek Konstruksi di Provinsi Jawa Timur Berdasarkan Kontrak Kerja. Narotama Jurnal Teknik Sipil, 21-31.
Latief, Y. (2001). Perencanaan dan Penjadwalan Konstruksi. Jakarta: Universitas Indonesia.
Leonda, G. (2008). Studi Keterlambatan Penyelesaian Proyek Konstruksi pada Tahun 2007 di Daerah Belitung. . Universitas Islam Indonesia Yogyakarta.
Listyaningsih, D., & Utomo, C. (2014). Pengaurh Keterlambatan Pembebasan Lahan Terhadap Keputusan Investasi Proyek Jalan Tol Surabaya-Mojokerto. Jurnal Teknik Pmots.
Maluku, P. T. (2018, Maret 2). Bendungan Way Apu Realisasi Program Strategis Nasional. Retrieved Juli 16, 2023, from Tribun Maluku: https://www.tribun-maluku.com/bendungan-way-apu-realisasi-program-strategis-nasional/03/02/
Marlijanto, S. D. (2010). Konsinyasi Ganti Rugi dalam Pengadaan Tanah untuk Kepentingan Umum (Studi Pengadaan Tanah untuk Pembangunan Proyek Jalan Tol Semarang - Solo di Kabupaten Semarang) . Doctoral Disertation, Universitas Diponegoro.
Mekanisari, N. (2009). Identifikasi Faktor Risiko Proses Pembebasan Tanah dalam Upaya Meningkatkan Kinerja Waktu pada Proyek Banjir Kanal Timur DKI Jakarta. Doctoral Dissertation, Universitas Indonesia.
Mirulewan, T. (2022, Juni 8). Kementerian LHK Didesak Selesaikan Persoalan Lahan Bendungan Temef. Retrieved Juli 16, 2023, from TVRI News: https://www.tvrinews.com/id/berita/t9781e4-kementerian-lhk-didesak-selesaikan-persoalan-lahan-bendungan-temef
Musra, A. (2014). Faktor-Faktor Penentu Keterlambatan Pembangunan Jalan Lingkar Utara Kota Solok. Jurnal Pembangunan Wilayah dan Kota, 70-82.
Nugroho, C. (2022, Desember 12). Target Meleset, Perampungan Bendungan Tiga Dihaji Molor ke 2025. Retrieved Juli 16, 2023, from okuselatan.disway: https://okuselatan.disway.id/read/639551/target-meleset-perampungan-bendungan-tiga-dihaji-molor-ke-2025
Partogi, M. (2015). Identifikasi Kinerja Kontraktor Berbasis Penerapan SIDLACOM (Studi Kasus : Balai Besar Pelaksanaan Jalan Nasional-I). Doctoral Dissertation, Universitas Gadjah Mada.
PP No 19 Tahun 2021. (2021). Tentang Penyelenggaraan Pengadaan Tanah Bagi Pembangunan untuk Kepentingan Umum.
Praboyo, B. (1998). Keterlambatan Waktu Pelaksanaan Proyek : Klasifikasi dan Peringkat dari Penyebab-Penyebabnya. Tesis Pasca Sarjana - Universitas Kristen Petra.
Priyadhi, G. W. (2006). Tesis: Faktor-Faktor yang Berpengaruh dalam Pembebasan Lahan Terhadap Kinerja Biaya pada Proyek Perumahan Sederhana di Kota Pekalongan dan Sekitarnya. Depok: Program Studi Teknik Sipil Kekhususan Manajemen Konstruksi, Program Pasca Sarjana Bidang Ilmu Teknik UI.
Redaksi. (2021, Februari 6). Konflik Lahan Waduk Krueng Keureuto Tuntas, Pembangunan Bisa Dilanjutkan. Retrieved Juli 16, 2023, from Info Aceh: https://infoaceh.net/aceh/konflik-lahan-waduk-krueng-keureuto-tuntas-pembangunan-bisa-dilanjutkan/
Redaksi. (2021, Januari 30). Penjelasan Pemkab Aceh Utara Soal Ganti Rugi Tanah Masyarakat Blang Pante di Waduk Keureuto. Retrieved Juli 16, 2023, from Portal Satu Kabar Aceh untuk Dunia: https://portalsatu.com/penjelasan-pemkab-aceh-utara-soal-ganti-rugi-tanah-masyarakat-blang-pante-di-waduk-keureuto/
Rosana, F. C. (2022, Juni 6). Proses Pembayaran Lahan di Bendungan Temef NTT Terhambat, Ini Penyebabnya. Retrieved Juli 16, 2023, from Tempo.co: https://bisnis.tempo.co/read/1598779/proses-pembayaran-lahan-di-bendungan-temef-ntt-terhambat-ini-penyebabnya
Rusdianto, E. (2018, September 2). Sengketa Harga Lahan Bendungan Pamukkulu Berujung di Pengadilan. Retrieved Juli 16, 2023, from Mongabay Situs Berita Lingkungan: https://www.mongabay.co.id/2018/09/02/sengketa-harga-lahan-bendungan-pamukkulu-berujung-di-pengadilan/
Sadono, S. (2006). Tesis: Faktor-Faktor yang Menghambat Pelaksanaan Pengadaan Tanah Terhadap Kinerja Waktu Proyek Pembangunan Jalan Tol. Depok: Program Studi Kekhususan Manajemen Konstruksi, Program Pasca Sarjana Bidang Ilmu Teknik UI.
Salle, A. (2007). Hukum Pengadaan Tanah untuk Kepentingan Umum. Yogyakarta: Kreasi Total Media.
Sani, A. (2008). Analisis Kapasitas Waduk dengan Metode Ripple dan Behaviour (Studi Kasus pada Waduk Mamak Sumbawa). Jurusan Teknik Sipil Universitas Muhammadiyah Yogyakarta.
Sanjaya, H., & Johari, G. J. (2021). Analisis Optimalisasi Perencanaan Kembali Durasi dan Biaya Proyek Menggunakan Metode Pertukaran Waktu dan Biaya. Jurnal Konstruksi, 347-354.
Santoso, N. B., S.T, M. S., & Sahid, I. M. (2017). Analisis Manajemen Risiko Pada Proyek Pembangunan Jalan Tol (Studi Kasus Proyek Pembangunan Jalan Tol Solo-Ngawi-Kertosono Ruas Ngawi-Kertosono Paket 3. Doctoral Dissertation, Universitas Muhammadiyah Surakarta.
Sarjita. (2005). Teknik dan Strategi Penyelesaian Sengketa Pertanahan. Yogyakarta: Tugu Jogja Pustaka.
Soeharto, I. (1997). Manajemen Proyek dari Konseptual sampai Operasional. Jakarta: Erlangga.
Sugiyono. (2012). Metode Penelitian Administrasi. Bandung: Alfabeta.
Sugiyono. (2017). Metode Penelitian Kuantitatif, Kualitatif dan R&D. Bandung: Alfabeta.
Supranto, J. (2000). Teknik Sampling untuk Survei dan Eksperimen. Jakarta: PT Rineka Cipta.
Wale, P. M., Jain, N. D., Godhani, N. R., Beniwal, S. R., & Mir, A. A. (2015). Planning and Scheduling of Project using Microsoft Project:Case Study of a Building in. IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE), Volume 12(Issue 3 Ver.III), 57-63.
Wirabakti, e. a. (2014). Studi Faktor-Faktor Keterlambatan Proyek Konstruksi Bangunan Gedung. Jurnal Konstruksi Vol. 6 No. 1.